How long does it take to build a lime kiln with a daily output of 100 tons
Constructing a lime vertical kiln with a daily output of 100 tons usually takes 3-4 months from the arrival of the construction team to the final completion of the construction.
In the preparation stage of construction, after the construction team enters the site, they will quickly carry out site investigation, planning and layout work, and at the same time, allocate and install construction equipment, as well as purchase and reserve materials required for construction, in order to fully prepare for the formal construction.
Entering the construction phase, the construction of the main structure of the shaft kiln is the core task, which requires precise construction techniques and strict quality control. At the same time, supporting auxiliary facilities such as raw material conveying systems and exhaust gas treatment devices will also be installed and constructed simultaneously to ensure the continuity of the entire production process.
In the later stage of construction, comprehensive equipment debugging and system integration will be carried out to test and optimize the various performance indicators of the shaft kiln, ensuring its stable operation. After a series of rigorous workflows, approximately 3-4 months later, a lime shaft kiln with a daily output of 100 tons that meets production requirements can be built and put into use.